§ 1710.203 Requirement to prepare a load forecast—distribution borrowers.

United States · 7 CFR — Agriculture · Status: effective

Get this as JSONEmbed this
Cite this
Citation
7 CFR 1710.203, § 1710.203 Requirement to prepare a load forecast—distribution borrowers, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/26936
Permanent ID
ys:prov:26936@1
SHA-256
b54d1e9dd030b8cb0ba2c6feacc8fd238b0e7b5e95070f980be3bad6de6bb66a

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) A distribution borrower that is a member of a power supply borrower, with a total utility plant of $500 million or more must provide a current (prepared within the last 2 years) load forecast in support of any request for RUS financial assistance. The distribution borrower may comply with this requirement by participation in and inclusion of its load forecasting information in the approved load forecast of its power supply borrower. (b) A distribution borrower that is a member of a power supply borrower which is itself a member of another power supply borrower that has a total utility plant of $500 million or more must provide a current (prepared within the last 2 years) load forecast in support of any request for RUS financial assistance. The distribution borrower may comply with this requirement by participation in and inclusion of its load forecasting information in the load forecast of its power supply borrower. (c) A distribution borrower that is a member of a power supply borrower with a total utility plant of less than $500 million must provide a current (prepared within the last 2 years) load forecast that meets the requirements of this subpart in support of an application for any RUS loan or loan guarantee that exceeds $3 million or 5 percent of total utility plant, whichever is greater. The distribution borrower may comply with this requirement by participation in and inclusion of its load forecasting information in the load forecast of its power supply borrower. (d) A distribution borrower with a total utility plant of less than $500 million and that is unaffiliated with a power supply borrower must provide a current (prepared within the last 2 years) load forecast that meets the requirements of this subpart in support of an application for any RUS loan or loan guarantee which exceeds $3 million or 5 percent of total utility plant, whichever is greater. (e) A distribution borrower with a total utility plant of $500 million or more must provide a current (prepared within the last 2 years) load forecast in support of any request for RUS financing assistance. The distribution borrower may comply with this requirement by participation in and inclusion of its load forecasting information in the load forecast of its power supply borrower.