7 CFR 1710.255
§ 1710.255 Energy efficiency work plans—energy efficiency borrowers.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 1710.255, § 1710.255 Energy efficiency work plans—energy efficiency borrowers, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/26951
- Permanent ID
ys:prov:26951@1- SHA-256
326e8bb1b9fc14fc792e90e1b60214c3db56475b41440f518e5d1cbc93cf0a97
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) All energy efficiency borrowers must maintain a current EEWP covering in aggregate all new construction, improvements, replacements, and retirements of energy efficiency related equipment and activities;
(b) An energy efficiency borrower's EEWP shall cover a period of between 2 and 4 years, and include all facilities to be constructed or improved which are eligible for RUS financing, whether or not RUS financial assistance will be sought or be available for certain facilities. The construction period covered by an EEWP in support of a loan application shall not be shorter than the loan period requested for financing of the facilities;
(c) The borrower's EEWP may only include facilities, equipment and other activities that have been approved by RUS as a part of an Eligible Energy Efficiency and Conservation Program pursuant to subpart H of this part;
(d) The borrower's EEWP must be consistent with the documentation provided as part of the current RUS approved EE Program as outlined in § 1710.410(c); and
(e) The borrower's EEWP must include an estimated schedule for the implementation of included projects.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.