7 CFR 1726.21
§ 1726.21 New materials.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 1726.21, § 1726.21 New materials, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/27212
- Permanent ID
ys:prov:27212@1- SHA-256
f45e3f2ed87340c1b9af89368698581bd51e3762db3922d0ded9f125e1d9abf6
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
The borrower shall purchase only new materials and equipment unless otherwise approved by RUS, on a case by case basis, prior to the purchase.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.