§ 1726.77 Substation and transmission line construction.

United States · 7 CFR — Agriculture · Status: effective

Get this as JSONEmbed this
Cite this
Citation
7 CFR 1726.77, § 1726.77 Substation and transmission line construction, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/27231
Permanent ID
ys:prov:27231@1
SHA-256
7bf22cc5acdee827754f6e054a8e4ae6fafcdf943e820b36e6603de7c9d7df2c

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Contract forms. The borrower must use RUS Form 830, Electric System Construction Contract—Project Construction, for construction of substations, except for minor modifications or improvements. (b) Procurement procedures. (1) It is the responsibility of each borrower to determine the procurement method that best meets its needs to award contracts in amounts of up to a cumulative total of $1,000,000 or four percent of NUP, whichever is greater, per calendar year of substation and transmission line construction (including minor modifications or improvements), exclusive of the cost of owner furnished materials and equipment. Borrowers may award Cost-Plus/Hourly contracts as part of these borrower responsibility limits up to a cumulative total of $500,000 or two percent of NUP, whichever is greater, per calendar year of substation and transmission line construction (including minor modifications or improvements), exclusive of the cost of owner furnished materials and equipment. (2) The borrower shall use formal competitive bidding for all other contract construction unless RUS specifically approves an alternative method. The dollar amount of contracts bid using the formal competitive bidding procedure do not apply to the cumulative total stipulated in paragraph (b)(1) of this section. (3) An amendment which increases the scope of the contract by adding a project is not considered competitively bid, therefore, the dollar amount of that amendment does apply to the cumulative total stipulated in paragraph (b)(1) of this section. (c) Contract approval. Individual contracts in the amount of $1,000,000 or more or four percent of NUP, whichever is greater, exclusive of the cost of owner furnished materials and equipment, are subject to RUS approval.