7 CFR 1726.150
§ 1726.150 Headquarters buildings.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 1726.150, § 1726.150 Headquarters buildings, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/27237
- Permanent ID
ys:prov:27237@1- SHA-256
6997e0dcd04fa5099d4a8c806950de01d14390b4e57533f441358f3e94ef7bb8
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
This section includes headquarters buildings such as warehouses and equipment service type buildings. Generating plant buildings are covered under subpart D of this part.
(a) Contract forms. The borrower must use RUS Form 257, Contract to Construct Buildings, for all contracts for construction of new headquarters facilities, and additions to, or modifications of existing headquarters facilities (except for minor modifications or improvements).
(b) Procurement procedures. A borrower may use Multiparty Lump Sum Quotations to award contracts in amounts of up to a cumulative total of $1,500,000 or four percent of NUP, whichever is greater, per calendar year of headquarters construction (including minor modifications or improvements). The borrower shall use formal competitive bidding for all other headquarters contract construction unless RUS specifically approves an alternative method.
(c) Contract approval. Contracts for headquarters construction are not subject to RUS approval and need not be submitted to RUS unless specifically requested by RUS on a case by case basis.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.