yourstate.us
La. Rev. Stat. § 39:125

Acceptance of project; guarantee period

Louisiana · Louisiana Revised Statutes Title 39 — Public Finance · Status: effective

Get this as JSONEmbed this
Cite this
Citation
La. Rev. Stat. § 39:125, Acceptance of project; guarantee period, Louisiana, version 1 as recorded 2026-10-04, yourstate.us, https://yourstate.us/provision/2724770
Permanent ID
ys:prov:2724770@1
SHA-256
9577de90776538fb7ccca891e88e9396819e6b53864fb3983392a7b33837837b

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

A. The facility planning and control section shall be responsible for directing final payment for work done on each project. However, if upon final inspection of any project it shall be found that the plans, specifications, contract, or change orders for the project shall not have been fully complied with, the facility planning and control section shall, until such compliance shall have been effected or adjustments satisfactory to it shall have been made, refuse to direct such payment. B. Upon completion of the project the facility planning and control section shall release it to the agency. The facility planning and control section shall be responsible for making an inspection of the project prior to the expiration of the guarantee period to observe any defects which may appear within one year after completion of the contract. The facility planning and control section shall give prompt written notice to the contractor of defects which are due to faulty materials and workmanship.