7 CFR 1726.253
§ 1726.253 Prior approved contract modification related to alternative bid provision for payment to contractor for bulk purchase of materials.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 1726.253, § 1726.253 Prior approved contract modification related to alternative bid provision for payment to contractor for bulk purchase of materials, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/27255
- Permanent ID
ys:prov:27255@1- SHA-256
7df90d290e452b859e18ce9c4588f824b718197687e97fd69776f5a8ff87a7f8
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
When construction is to be performed over an extended period of time, but large quantities of material are to be purchased by the contractor at the beginning of the project (e.g., cable for URD installations), the borrower may allow alternative bids providing for payment to the contractor of 90 percent of the cost of such materials within 30 days of delivery of those materials at the job site. The borrower will retain the right to award the contract with or without the alternative payment provision, however, the contract still must be awarded on the basis of the lowest evaluated responsive bid for the alternative accepted.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.