7 CFR 1753.5
§ 1753.5 Methods of major construction.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 1753.5, § 1753.5 Methods of major construction, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/27694
- Permanent ID
ys:prov:27694@1- SHA-256
f18b6b675c5eed99958cc6bd7ca459485c036fea7055d718fb7b510e9489cc07
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) All major construction projects financed by loan funds shall be performed pursuant to a contract approved by RUS and awarded through sealed competitive bidding unless
(1) A specific exception is granted in subparts D, E, F, G, or H, or
(2) Written RUS approval is obtained.
(b) Contract construction.
(1) RUS approval of the borrower's award of the contract is not required if the contractor is selected through sealed competitive bidding, the bid amount is $500,000 or less and the contractor is not a company or organization affiliated with the borrower. This does not relieve the borrower of the requirements of bidding or bid evaluation set contained in this part.
(2) RUS approval of the borrower's award of the contract is required for all other competitively-bid and for negotiated major construction contracts.
(3) The requirements and procedures for sealed competitive bidding are presented in § 1753.8(a). The requirements and procedures for negotiation are presented in § 1753.8(b).
(c) Force account construction. To obtain RUS approval of the force account method for major construction the borrower must demonstrate its ability to perform major construction based on past force account construction which fully met RUS construction standards and was as cost-effective as contract construction in the area. If the borrower has no record of past performance to support its request, but has adequate equipment and experienced personnel to perform the proposed construction, RUS may approve a small trial project. The requirements and procedures for force account construction are presented in subparts D, E, G, and H.