7 CFR 1784.26
§ 1784.26 Planning, development, and procurement.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 1784.26, § 1784.26 Planning, development, and procurement, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/28234
- Permanent ID
ys:prov:28234@1- SHA-256
6332bf10ccc91581371a52a7d46fb9b626cb783ce6d2870e545be64f7b1d5132
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) If RUS is the lead agency and will provide oversight for the project, a certification should be obtained from the State agency, or the Environmental Protection Agency if the State does not have primacy, stating that the proposed improvements will be in compliance with requirements of the Safe Drinking Water Act and/or Clean Water Act and the applicable requirements of 2 CFR part 200 and 2 CFR part 400.
(b) Applicants that will bid and construct a project in phases, must provide assurance that the full scope of each specific phase of the project will be functional. In the event that the actual cost is anticipated to exceed the funding originally allocated for the project, all potential options will be reviewed and considered, including but not limited to acquiring additional funds or a reduction in project scope. RUS, ANTHC, and VSW will ensure that all items that were funded and within the scope of the project, including all phases, are functional when all funds have been disbursed.