7 CFR 1786.157
§ 1786.157 Approval of applications.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 1786.157, § 1786.157 Approval of applications, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/28311
- Permanent ID
ys:prov:28311@1- SHA-256
e7446ceec816f25abe02ef6b290ff68dfc75f783fa31b9da55c9f73a67b8f7c9
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Ordinarily, within 30 days of receipt, an application will be reviewed and the borrower will be notified as to whether the application has been approved. If the application has not been approved, the borrower will be informed as to the reasons. If the application is approved the borrower shall thereafter be provided with a prepayment agreement for execution.
(b) The Administrator may limit the number of applications approved and closings scheduled from time to time, taking into account, among other matters, administrative considerations of the RUS.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.