7 CFR 5001.513
§ 5001.513 Interest rate changes.
United States · 7 CFR — Agriculture · Status: effective
Cite this
- Citation
- 7 CFR 5001.513, § 5001.513 Interest rate changes, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/31738
- Permanent ID
ys:prov:31738@1- SHA-256
a9fc981f4272dcea7ce71f84d05c3ef71963f0fd5eaeae4305ec1bd9e853d864
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Interest rate freezes. The guaranteed loan interest rate will freeze at the earliest uncured default date and will remain unchanged until the cancellation of the loan note guarantee in compliance with § 5001.524.
(b) Reductions. The borrower, lender, and holder (if any) may collectively initiate a permanent or temporary reduction in the interest rate of the guaranteed loan at any time during the life of the loan upon written agreement among these parties. After a permanent reduction, the loan note guarantee will only cover losses of interest at the reduced interest rate.
(1) When the Agency is a holder, the lender must obtain Agency approval before implementing the reduction. The lender must provide a copy of the modification agreement to the Agency for approval. The Agency will approve the reduction only when it is demonstrated that the change is more viable than liquidation and that the government's financial interests are not adversely affected.
(2) Factors that the Agency will consider in determining whether to approve the change are the Government's cost of borrowing money; the monetary recovery is greater than the liquidation recovery; and the project's continued viability as demonstrated by a financial feasibility analysis.
(c) Increases. Unless a temporary interest rate reduction occurred, increases in fixed interest rates and increases in variable interest rate structure are prohibited.
(d) Fixed rate to variable rate change. Fixed rates can be changed to variable rates to reduce the borrower's interest rate only when the variable rate has a ceiling that is less than or equal to the original fixed rate.
(e) Variable rate to fixed rate change. Variable rates can be changed to a fixed rate at the request of the borrower, agreement of the holder, if any, and Agency concurrence.
(f) After adjustments. The interest rates, after adjustments, must comply with the requirements for interest rates on new loans as established by paragraph § 5001.401.
(g) Documentation. The lender is responsible for the legal documentation of interest rate changes by an endorsement or any other legally effective amendment to the promissory note; however, no new promissory notes can be issued. The lender must provide copies of all such documents to the Agency within 10 calendar days of the change.
(3) In a final loss settlement when qualifying interest rate changes are made in compliance with this part, the lender must calculate interest based on the periods the given rates were in effect. The lender must maintain records that adequately document the accrued interest claimed, which must be determined in accordance with § 5001.450(c).
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.