10 CFR 2.109
§ 2.109 Effect of timely renewal application.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 2.109, § 2.109 Effect of timely renewal application, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/35776
- Permanent ID
ys:prov:35776@1- SHA-256
38bbf5afb94b1bafe6d2fc59d029ef9c23fae8e9002a649829e472d6b98dccbd
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Except for the renewal of licenses identified in paragraphs (b) through (f) of this section, if at least 30 days before the expiration of an existing license authorizing any activity of a continuing nature, the licensee files an application for a renewal or for a new license for the activity so authorized, the existing license will not be deemed to have expired until the application has been finally determined.
(b) If the licensee of a nuclear power plant licensed under § 50.21(b) or § 50.22 or under subpart H of part 53 of this chapter files a sufficient application for renewal of either an operating license or a combined license at least 5 years before the expiration of the existing license, the existing license will not be deemed to have expired until the application has been finally determined.
(c) If the holder of an early site permit licensed under subpart A of part 52 or under subpart H of part 53 of this chapter, as applicable, files a sufficient application for renewal under § 52.29 or § 53.1173 of this chapter, as applicable, at least 12 months before the expiration of the existing early site permit, the existing permit will not be deemed to have expired until the application has been finally determined.
(d) If the licensee of a manufacturing license under subpart F of part 52 or under subpart H of part 53 of this chapter files a sufficient application for renewal under § 52.177 or § 53.1295 of this chapter at least 12 months before the expiration of the existing license, the existing license will not be deemed to have expired until the application has been finally determined.
(e) If the licensee of an Independent Spent Fuel Storage Installation (ISFSI) licensed under subpart C of part 72 of this chapter files a sufficient application for renewal under § 72.42 of this chapter at least 2 years before the expiration of the existing license, the existing license will not be deemed to have expired until the application has been finally determined.
(f) If the licensee of a non-power production or utilization facility licensed under 10 CFR 50.22, or a testing facility, files a sufficient application for renewal at least 2 years before the expiration of the existing license, the existing license will not be deemed to have expired until the application has been finally determined.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.