10 CFR 2.819
§ 2.819 Denial of application for failure to supply information.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 2.819, § 2.819 Denial of application for failure to supply information, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/35900
- Permanent ID
ys:prov:35900@1- SHA-256
626c514e3a2045b0fa921dd8b61d03cf7a2daca280ca32dd249820dd4ec8442e
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The Commission may deny an application for a standard design certification if an applicant fails to respond to a request for additional information within 30 days from the date of the request, or within such other time as may be specified.
(b) If the Commission denies an application because the applicant has failed to respond in a timely fashion to a request for additional information, the NRC will publish in the Federal Register a notice of denial and will notify the applicant with a simple statement of the grounds of denial. If a notice of receipt of application, advance notice of proposed rulemaking, or notice of proposed rulemaking for a standard design certification was published on the NRC Web site, then the notice of action on the denial will also be published on the NRC Web site.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.