10 CFR 25.19

§ 25.19 Processing applications.

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 25.19, § 25.19 Processing applications, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/36599
Permanent ID
ys:prov:36599@1
SHA-256
b974c999d5314d5b5b56b4854c7687bfcc95b0b71ce5a77e38fbc9a35b144faf

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Each application for an access authorization or access authorization renewal must be submitted to the CSA. If the NRC is the CSA, the application and its accompanying fee must be submitted to the NRC Division of Facilities and Security. If necessary, the NRC Division of Facilities and Security may obtain approval from the appropriate Commission office exercising licensing or regulatory authority before processing the access authorization or access authorization renewal request. If the applicant is disapproved for processing, the NRC Division of Facilities and Security shall notify the submitter in writing and return the original application (security packet) and its accompanying fee.