Appendix C to Subpart A of Part 51—Environmental Effect of Issuing a Permit or License for a New Nuclear Reactor
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR — Energy, Appendix C to Subpart A of Part 51—Environmental Effect of Issuing a Permit or License for a New Nuclear Reactor, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37437
- Permanent ID
ys:prov:37437@1- SHA-256
118d24e445e0d83a2060ffe5edf6ed57fb7384aba6a34cb7d18d6aa4823bda0d
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
The Commission has assessed the environmental impacts associated with authorizing the construction, operation, and decommissioning of a nuclear reactor. Table C-1 summarizes the Commission's generic findings on the scope and magnitude of environmental impacts of such an authorization as required by section 102(2) of the National Environmental Policy Act of 1969, as amended. Table C-1 presents the results of the generic analysis of those environmental impacts associated with building, 1 operating, and decommissioning a nuclear reactor that the NRC has designated as Category 1, as well as listing the issues that could not be resolved generically, designated as Category 2. The use of this table by applicants will be in accordance with § 51.50(d), and the use by the staff will be in accordance with §§ 51.75(d) and 51.96. On a 10-year cycle, the Commission intends to review the material in this appendix and update it if necessary. A scoping notice must be published in the Federal Register indicating the results of the NRC's review and inviting public comments and proposals for other areas that should be updated.
1 The term “building,” as used in the NR GEIS, includes the full range of preconstruction (building activities not within the NRC's regulatory authority), and construction and installation activities (building activities within the NRC's regulatory authority).
Table C-1—Summary of Findings on Environmental Issues for Issuing a Permit or License for a New Nuclear Reactor 1
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.