§ 52.31 Criteria for renewal.

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 52.31, § 52.31 Criteria for renewal, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37467
Permanent ID
ys:prov:37467@1
SHA-256
863f8ebf15eb9a4a3424243f7983ec501927c3b9691209558c6b1ba33b130b8f

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) The Commission shall grant the renewal only if it determines that: (1) The site complies with the Act, the Commission's regulations, and orders applicable and in effect at the time the site permit was originally issued; and (2) Any new requirements the Commission may wish to impose are: (i) Necessary for adequate protection to public health and safety or common defense and security; (ii) Necessary for compliance with the Commission's regulations, and orders applicable and in effect at the time the site permit was originally issued; or (iii) A substantial increase in overall protection of the public health and safety or the common defense and security to be derived from the new requirements, and the direct and indirect costs of implementation of those requirements are justified in view of this increased protection. (b) A denial of renewal under the provisions of § 52.31(a) does not bar the permit holder or another applicant from filing a new application for the site which proposes changes to the site or the way that it is used to correct the deficiencies cited in the denial of the renewal.