10 CFR 52.133
§ 52.133 Relationship to other subparts.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 52.133, § 52.133 Relationship to other subparts, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37512
- Permanent ID
ys:prov:37512@1- SHA-256
cb1d616bb7442766d221fbd53f07ffcd3f68b7fb0a789780c12bcc044fded5f3
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) This subpart applies to a person that requests a standard design approval from the NRC staff separately from an application for a construction permit filed under 10 CFR part 50 or a combined license filed under subpart C of this part. An applicant for a construction permit or combined license may reference a standard design approval.
(b) Subpart B of this part governs the certification by rulemaking of the design of a nuclear power plant. Subpart B may be used independently of the provisions in this subpart.
(c) Subpart F of this part governs the issuance of licenses to manufacture nuclear power reactors to be installed and operated at sites not identified in the manufacturing license application. Subpart F of this part may be used independently of the provisions in this subpart.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.