yourstate.us
10 CFR 52.153

§ 52.153 Relationship to other subparts.

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 52.153, § 52.153 Relationship to other subparts, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37523
Permanent ID
ys:prov:37523@1
SHA-256
6e8aa57bb6761997c25c9fa73f6be939081af6cc1984148f1f08758c5501ef54

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) A nuclear power reactor manufactured under a manufacturing license issued under this subpart may only be transported to and installed at a site for which either a construction permit under part 50 of this chapter or a combined license under subpart C of this part has been issued. (b) Subpart B of this part governs the certification by rulemaking of the design of standard nuclear power facilities. Subpart E of this part governs the NRC staff review and approval of standard designs for a nuclear power facility. A manufacturing license applicant may reference a standard design certification or a standard design approval in its application. These subparts may also be used independently of the provisions in this subpart.