10 CFR 53.1170
§ 53.1170 Transfer of early site permit.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 53.1170, § 53.1170 Transfer of early site permit, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37670
- Permanent ID
ys:prov:37670@1- SHA-256
3cf7bbfb2a41f7b51ef203c99c889c9f4c99ea1f0b99ff414120b1a0356fad0f
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
An application to transfer an early site permit will be processed under § 53.1570.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.