yourstate.us
10 CFR 53.1306

§ 53.1306 Contents of applications for construction permits; general information.

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 53.1306, § 53.1306 Contents of applications for construction permits; general information, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37708
Permanent ID
ys:prov:37708@1
SHA-256
0eeec9ee4e16d5907b5846caf1fdf55625bc5d8c23fa153666182de220253406

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

An application for a CP must include the information required by § 53.1109 and the following information: (a) Information sufficient to demonstrate to the Commission the financial qualification of the applicant to carry out, under the regulations in this chapter, the activities for which the permit is sought. As applicable, the applicant should provide information that demonstrates that the applicant appears to be financially qualified to cover estimated construction costs and related fuel cycle costs, including estimates of the total construction costs and related fuel cycle costs of the facility, a financial capacity plan, and any source(s) of funds available at the time of application to cover these costs. If available funding at the time of application is 50 percent or less, the applicant should include proposed license conditions to facilitate verification that funding is available prior to the start of construction. (b) If the applicant proposes to construct or alter a facility, the application must state the earliest and latest dates for completion of the construction or alteration.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.