10 CFR 53.1336

§ 53.1336 Finality of construction permits.

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 53.1336, § 53.1336 Finality of construction permits, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37717
Permanent ID
ys:prov:37717@1
SHA-256
7fdb671751b5950da9c8268fe70591575b54c95f3e38f9f9f7c694ae14042929

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Notwithstanding any provision in § 53.1590, a CP constitutes an authorization to proceed with construction but does not constitute Commission approval of the safety of any design feature or specification unless the applicant specifically requests such approval and such approval is incorporated in the permit. The applicant, at its option, may request such approvals in the CP or by amendment to the CP. If approved by the NRC and included in the permit, the NRC will consider modifications to the approved design features or specifications in accordance with § 53.1590.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.