10 CFR 53.1342
§ 53.1342 Duration of construction permits.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 53.1342, § 53.1342 Duration of construction permits, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37718
- Permanent ID
ys:prov:37718@1- SHA-256
bbfd9e477a056b08bf96c1feaf9f45c6b5755f8cf5760604d673781fec8bcd9a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) A CP will state the earliest and latest dates for completion of construction or alteration of the facility, not to exceed 40 years from date of issuance.
(b) If the proposed construction or alteration of the facility is not completed by the latest completion date, the CP shall expire, and all rights are forfeited. However, upon good cause shown, the Commission will extend the completion date for a reasonable period of time. The Commission will recognize, among other things, developmental problems attributed to the experimental nature of the facility or fire, flood explosion, strike, sabotage, domestic violence, enemy action an act of the elements, and other acts beyond the control of the permit holder, as a basis for extending the completion date.