10 CFR 53.1419
§ 53.1419 Contents of applications for combined licenses; other application content.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 53.1419, § 53.1419 Contents of applications for combined licenses; other application content, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37737
- Permanent ID
ys:prov:37737@1- SHA-256
90d4c6c0ff6979bd6f998c3ba5f45a2315c650fac7a23fe1b7ac5087768ca40a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) In addition to the FSAR, the application must also include the following:
(1) Environmental report.
(i) An environmental report either in accordance with § 51.50(c) of this chapter if an LWA under § 53.1130 is not requested in conjunction with the COL application, or in accordance with §§ 51.49 and 51.50(c) of this chapter if an LWA is requested in conjunction with the COL application; or
(ii) If the applicant wishes to request that an LWA under § 53.1130 be issued before issuance of the COL, the information otherwise required by § 53.1130, in accordance with either § 2.101(a)(1) through (a)(4), or § 2.101(a)(9) of this chapter;
(2) Availability controls (if not included in the FSAR). A description of the controls on plant operations, including availability controls, to provide reasonable confidence of safe operation and that the configurations and special treatments for SR SSCs and NSRSS SSCs provide the capabilities and reliabilities required to satisfy the safety criteria of § 53.220 if not addressed by Technical Specifications under § 53.1416(a)(25); and
(3) Inspections, tests, analyses, and acceptance criteria. The proposed inspections, tests, and analyses, including those applicable to emergency planning, that the licensee must perform, and the acceptance criteria that are necessary and sufficient to provide reasonable assurance that, if the inspections, tests, and analyses are performed and the acceptance criteria met, the facility has been constructed and will be operated in conformity with the COL, the provisions of the Act, and the Commission's rules and regulations.
(i) If the application references an early site permit with ITAAC, the early site permit ITAAC must apply to those aspects of the COL which are approved in the early site permit.
(ii) If the application references a standard design certification, the ITAAC contained in the certified design must apply to those portions of the facility design which are approved in the standard design certification.
(iii) If the application references an ML, the ITAAC contained in the ML must apply to those portions of the facility design which are approved in the ML.
(iv) If the application references an early site permit with ITAAC, a standard design certification, an ML, or a combination thereof, the application may include a notification that a required inspection, test, or analysis in the ITAAC has been successfully completed and that the corresponding acceptance criterion has been met. The Federal Register notice required by § 53.1422 of this chapter must indicate that the application includes this notification.
(b) [Reserved]
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.