10 CFR 60.41
§ 60.41 Standards for issuance of a license.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 60.41, § 60.41 Standards for issuance of a license, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37885
- Permanent ID
ys:prov:37885@1- SHA-256
df433b033cf9cb2d7f3c1f5004349a4636d519b6d3b6bc1bcea81a1b499091d5
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
A license to receive and possess source, special nuclear, or byproduct material at a geologic repository operations area may be issued by the Commission upon finding that:
(a) Construction of the geologic repository operations area has been substantially completed in conformity with the application as amended, the provisions of the Atomic Energy Act, and the rules and regulations of the Commission. Construction may be deemed to be substantially complete for the purposes of this paragraph if the construction of (1) surface and interconnecting structures, systems, and components, and (2) any underground storage space required for initial operation are substantially complete.
(b) The activities to be conducted at the geologic repository operations area will be in conformity with the application as amended, the provisions of the Atomic Energy Act and the Energy Reorganization Act, and the rules and regulations of the Commission.
(c) The issuance of the license will not be inimical to the common defense and security and will not constitute an unreasonable risk to the health and safety of the public.
(d) All applicable requirements of part 51 have been satisfied.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.