10 CFR 60.141
§ 60.141 Confirmation of geotechnical and design parameters.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 60.141, § 60.141 Confirmation of geotechnical and design parameters, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/37925
- Permanent ID
ys:prov:37925@1- SHA-256
b4834db4b70aa6bb4f9c375a64629f62c04874a6572988871215e8949cbc3749
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) During repository construction and operation, a continuing program of surveillance, measurement, testing, and geologic mapping shall be conducted to ensure that geotechnical and design parameters are confirmed and to ensure that appropriate action is taken to inform the Commission of changes needed in design to accommodate actual field conditions encountered.
(b) Subsurface conditions shall be monitored and evaluated against design assumptions.
(c) As a minimum, measurements shall be made of rock deformations and displacement, changes in rock stress and strain, rate and location of water inflow into subsurface areas, changes in groundwater conditions, rock pore water pressures including those along fractures and joints, and the thermal and thermomechanical response of the rock mass as a result of development and operations of the geologic repository.
(d) These measurements and observations shall be compared with the original design bases and assumptions. If significant differences exist between the measurements and observations and the original design bases and assumptions, the need for modifications to the design or in construction methods shall be determined and these differences and the recommended changes reported to the Commission.
(e) In situ monitoring of the thermomechanical response of the underground facility shall be conducted until permanent closure to ensure that the performance of the natural and engineering features are within design limits.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.