10 CFR 205.301

§ 205.301 Time of filing.

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 205.301, § 205.301 Time of filing, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/39009
Permanent ID
ys:prov:39009@1
SHA-256
2830321ec451e958957b02c57e0fb9fe7314b03c7f1d2460bb81fa6d7c264304

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Each application should be made at least six months in advance of the initiation of the proposed electricity export, except when otherwise permitted by the ERA to resolve an emergency situation.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.