10 CFR 217.36
§ 217.36 Changes or cancellations of priority ratings and rated orders.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 217.36, § 217.36 Changes or cancellations of priority ratings and rated orders, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/39112
- Permanent ID
ys:prov:39112@1- SHA-256
1656326b8dab3f69ebbdeb2b7d3bc7e06c061e7dbc38a51e12c0ebea6546532c
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The priority rating on a rated order may be changed or canceled by:
(1) An official action of the Department of Energy; or
(2) Written notification from the person who placed the rated order.
(b) If an unrated order is amended so as to make it a rated order, or a DO rating is changed to a DX rating, the supplier must give the appropriate preferential treatment to the order as of the date the change is received by the supplier.
(c) An amendment to a rated order that significantly alters a supplier's original production or delivery schedule shall constitute a new rated order as of the date of its receipt. The supplier must accept or reject the amended order according to the provisions of § 217.33.
(d) The following amendments do not constitute a new rated order: a change in shipping destination; a reduction in the total amount of the order; an increase in the total amount of the order which has negligible impact upon deliveries; a minor variation in size or design; or a change which is agreed upon between the supplier and the customer.
(e) If a person no longer needs items or services to fill a rated order, any rated orders placed with suppliers for the items or services, or the priority rating on those orders, must be canceled.
(f) When a priority rating is added to an unrated order, or is changed or canceled, all suppliers must be promptly notified in writing.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.