10 CFR 436.35
§ 436.35 Standard terms and conditions.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 436.35, § 436.35 Standard terms and conditions, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/39762
- Permanent ID
ys:prov:39762@1- SHA-256
229d116def9f9562ca885ab5d0eb5c45dff563290708ef4ffef3f7fb4bf57266
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Mandatory requirements. In addition to contractual provisions otherwise required by the Act or this subpart, any energy savings performance contract shall contain clauses—
(1) Authorizing modification, replacement, or changes of equipment, at no cost to the Federal agency, with the prior approval of the contracting officer who shall consider the expected level of performance after such modification, replacement or change;
(2) Providing for the disposition of title to systems and equipment;
(3) Requiring prior approval by the contracting officer of any financing agreements (including lease-acquisitions) and amendments to such an agreement entered into after contract award for the purpose of financing the acquisition of energy conservation measures;
(4) Providing for an annual energy audit and identifying who shall conduct such an audit, consistent with § 436.37 of this subpart; and
(5) Providing for a guarantee of energy cost savings to the Federal agency, and establishing payment schedules reflecting such guarantee.
(b) Third party financing. If there is third party financing, then an energy savings performance contract may contain a clause:
(1) Permitting the financing source to perfect a security interest in the installed energy conservation measures, subject to and subordinate to the rights of the Federal agency; and
(2) Protecting the interests of a Federal agency and a financing source, by authorizing a contracting officer in appropriate circumstances to require a contractor who defaults on an energy savings performance contract or who does not cure the failure to make timely payments, to assign to the financing source, if willing and able, the contractor's rights and responsibilities under an energy savings performance contract;
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.