10 CFR 503.7
§ 503.7 State approval—general requirement for new powerplants.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 503.7, § 503.7 State approval—general requirement for new powerplants, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/40046
- Permanent ID
ys:prov:40046@1- SHA-256
e822ec07781dd68be9e183593aa2779850ee69c0850db4b33b20da9567ff13fd
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Where approvals by the appropriate State regulatory authority are required prior to the construction or use of a new powerplant, a petition for an exemption for consideration by OFE may be submitted to OFE prior to obtaining such approvals from the State regulatory authority.
(b) An exemption granted for a powerplant shall not become effective until an adequate demonstration has been made to OFE that all applicable approvals required by the State regulatory authorities have been obtained.
Legislative history