§ 503.11 Alternative sites—general requirement for permanent exemptions for new powerplants.

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 503.11, § 503.11 Alternative sites—general requirement for permanent exemptions for new powerplants, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/40050
Permanent ID
ys:prov:40050@1
SHA-256
6fc46472beb545fc2903ec2c0c207cede15222aa41adad749bd91e32ffa98f2c

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Criteria. To qualify for permanent exemption due to lack of alternate fuel supply, site limitations, environmental requirements, or inadequate capital, section 212(a) of the Act requires a demonstration that one of these exemptions would be available for any reasonable alternative site for the facility. (b) Evidence. The petition must include the following evidence in order to make the demonstration required by this section: (1) Duly executed certifications to the criteria set forth in paragraph (a) of this section; and (2) Exhibits containing the basis for the certifications submitted under this section (including those factual and analytical materials deemed by the petitioner to be sufficient to support its certifications to this general requirement).