§ 611.102 Eligible project costs.

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 611.102, § 611.102 Eligible project costs, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/40243
Permanent ID
ys:prov:40243@1
SHA-256
27408bbafafcd4ba5b09a3894abf9d6bcf53ae4737d026658107db27f05e0e3d

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Eligible costs are: (1) Those costs that are reasonably related to the reequipping, expanding, or establishing a manufacturing facility in the United States to produce qualifying advanced technology vehicles or qualifying components; (2) Costs of engineering integration performed in the United States for qualifying vehicles or qualifying components; (3) Costs for payment with loan proceeds that are incurred, but not yet paid by the borrower, after a substantially complete application has been submitted to DOE; and (4) Costs incurred after closing of the loan. (b) In determining the overall total cost of an Eligible Project, DOE and the applicant may include significant costs already incurred and capitalized by the applicant in accordance with Generally Accepted Accounting Principles and these costs may be considered by DOE in determining the Borrower's contribution to total project costs.

Legislative history