10 CFR 719.17
§ 719.17 Are there any budgetary requirements?
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 719.17, § 719.17 Are there any budgetary requirements?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/40487
- Permanent ID
ys:prov:40487@1- SHA-256
d43dce92a36c945c49d4c3b03b350ef133bcae827b105461601f2db397d344ee
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Contractors required to submit a Legal Management Plan must also submit an annual legal budget to Department Counsel.
(b) The annual legal budget must include cost projections for significant matters at a level of detail reflective of the types of billable activities and the stage of each such matter.
(c) For informational purposes for both the contractor and Department Counsel, the contractor must submit a report to Department Counsel comparing its budgeted and actual legal costs within 30 days of the conclusion of the period covered by each annual legal budget. The Department recognizes, however, that there may be departures from the annual budget beyond the control of the contractor.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.