yourstate.us
10 CFR 820.14

§ 820.14 Whistleblower protection.

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 820.14, § 820.14 Whistleblower protection, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/40771
Permanent ID
ys:prov:40771@1
SHA-256
a33908f1839d71ca66d37ca078036e415f475fdd9541b1f66931622661cf8dd6

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Covered acts. An act of retaliation (as defined in 10 CFR 708.2) by a DOE contractor, prohibited by 10 CFR 708.43, that results from a DOE contractor employee's involvement in an activity listed in 10 CFR 708.5(a) through (c) may constitute a violation of a DOE Nuclear Safety Requirement if it concerns nuclear safety. (b) Commencement of investigation. The Director may not initiate an investigation or take any other action under this part with respect to an alleged act of retaliation by a DOE contractor until 180 days after an alleged violation of 10 CFR 708.43 occurs. (c) Administrative or judicial proceedings. The Director shall immediately suspend any ongoing activities under this part and suspend any time limits under this part when an administrative or judicial proceeding commences based on the same alleged act of retaliation. While an administrative or judicial proceeding, including appeals, is pending, the Director may not exercise any authority under this part based on an alleged violation of 10 CFR 708.43, including issuing enforcement letters, subpoenas, orders to compel attendance, Consent Orders, Preliminary Notices of Violation, or Final Notices of Violation. Once such a proceeding commences, the Director shall not conduct any activities under this part until sixty days after a final decision of an agency or court finds that a retaliation occurred, or otherwise makes a final disposition of the matter on procedural grounds without explicitly finding that retaliation did not occur. (d) Final decision. For the purposes of this section, a final decision of an agency or court includes any of the following: (1) A final agency decision pursuant to 10 CFR part 708; (2) A final decision or order of the Secretary of Labor pursuant to 29 CFR part 24; (3) A decision by the Secretary upon a report by the Inspector General; (4) A decision by a federal or state court. (e) Evidentiary record. If a final decision of an agency or court finds that retaliation occurred, the Director may obtain and use information collected as part of those proceedings. The Director has discretion to give appropriate weight to information obtained from these proceedings and to initiate and conduct further investigation if the Director deems necessary, particularly with regard to the relationship between the retaliation and nuclear safety. (f) Underlying nuclear safety requirements. Notwithstanding the commencement of an administrative or judicial proceeding based on an alleged act of retaliation, this section shall not prevent the Director from taking any action consistent with this part regarding compliance with DOE Nuclear Safety Requirements other than 10 CFR 708.43.