10 CFR 904.6
§ 904.6 Charge for capacity and firm energy.
United States · 10 CFR — Energy · Status: effective
Cite this
- Citation
- 10 CFR 904.6, § 904.6 Charge for capacity and firm energy, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/41085
- Permanent ID
ys:prov:41085@1- SHA-256
b7088a13745107dc40c0384a8dccd98dae12ff7201d55dd8aef8f82b31e0e9cb
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
The charge for Capacity and Firm Energy from the Project shall be composed of two separate charges; a charge to provide for the basic revenue requirements, as identified in paragraphs (b), (c), and (d) of § 904.5 of these General Regulations (Base Charge), and a charge to provide the surplus revenue for the Lower Colorado River Basin Development Fund contribution, as identified in paragraph (e) of § 904.5 of these General Regulations (Lower Basin Development Fund Contribution Charge).
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.