10 CFR 905.19

§ 905.19 How are plans and reports reviewed and approved?

United States · 10 CFR — Energy · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 CFR 905.19, § 905.19 How are plans and reports reviewed and approved?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/41108
Permanent ID
ys:prov:41108@1
SHA-256
002b6e196558f2f924a8f1e0df3c9bf5a1412f81a942cdbdb20febe2a4d080a4

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Western will review all plans and reports submitted under this subpart and notify the submitting entity of the plan's or report's acceptability within 120 days after receiving it. If a plan or report submittal is insufficient, Western will provide a notice of deficiencies to the entity that submitted the plan or report. Western, working together with the entity, will determine the time allowable for resubmitting the plan or report. However, the time allowed for resubmittal will not be greater than 9 months after the disapproval date, unless otherwise provided by applicable contract language.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.