Western will extend resource commitments for 20 years from the date existing contracts expire to existing customers with long-term firm power contracts from projects identified in section 905.30(b).

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.