yourstate.us
10 U.S.C. § 4251

Major defense acquisition programs: factors to be considered before Milestone A approval

United States · Title 10 — ARMED FORCES · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 U.S.C. § 4251, Major defense acquisition programs: factors to be considered before Milestone A approval, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/434892
Permanent ID
ys:prov:434892@1
SHA-256
21b6d93b108e5343953ca4dcbe036b50a05a2c8f9093fd0227fa0c7ac03a24ae

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Before granting Milestone A approval for a major defense acquisition program or a major subprogram, the milestone decision authority for the program or subprogram shall ensure that— A major defense acquisition program or subprogram may not receive Milestone A approval or otherwise be initiated prior to Milestone B approval until the milestone decision authority confirms that the following factors were considered in the decision to grant Milestone A approval: In this section:

Legislative history