yourstate.us
10 U.S.C. § 6287

Matters relating to critical decisions

United States · Title 10 — ARMED FORCES · Status: effective

Get this as JSONEmbed this
Cite this
Citation
10 U.S.C. § 6287, Matters relating to critical decisions, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/435215
Permanent ID
ys:prov:435215@1
SHA-256
c644123ff6a874eab9c1eecf0b3236cc6aac9dad9ea0dd46414cddc22da68283

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

After the date on which a plant project specifically authorized by law and carried out under Department of Energy Order 413.3B (relating to program management and project management for the acquisition of capital assets), or a successor order, achieves critical decision 2, the Administrator may not change the requirements for such project if such change increases the cost of such project by more than the lesser of $5,000,000 or 15 percent, unless— the Administrator submits to the congressional defense committees— a cost-benefit and risk analysis of such proposed change, including with respect to—

Legislative history

The public laws that enacted or amended this section. Tallies are for the whole bill as it passed each chamber — often an omnibus covering far more than this provision — not a vote on this section alone.

  • Enacted byPub. L. 119-60(S. 1071)2025-12-18
    National Defense Authorization Act for Fiscal Year 2026
    House: 312–112Senate: no recorded tally