Hydroelectric generating facilities; lists, transmittal to Congress; construction schedule and cost estimates for expedited construction program; prospective accomplishments from expedited completion of facilities; statement of appropriated but not obligated funds
United States · Title 15 — COMMERCE AND TRADE · Status: effective
Cite this
- Citation
- 15 U.S.C. § 783, Hydroelectric generating facilities; lists, transmittal to Congress; construction schedule and cost estimates for expedited construction program; prospective accomplishments from expedited completion of facilities; statement of appropriated but not obligated funds, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/440802
- Permanent ID
ys:prov:440802@1- SHA-256
6278c0c6ac47b218ccc37fc696c89b3a7bd8234c93fec49e58debf95a6054e31
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Within ninety days of the effective date of this chapter, the Administrator of the Federal Energy Administration, in consultation with the Secretary of the Interior and the Secretary of the Army, shall—
transmit to the Congress—
provide, for each such facility which is listed—
Legislative history
The public laws that enacted or amended this section. Tallies are for the whole bill as it passed each chamber — often an omnibus covering far more than this provision — not a vote on this section alone.
- Federal Energy Administration Act of 1974House: no recorded tallySenate: no recorded tally