33 U.S.C. § 598c
Easements for hurricane and storm damage reduction projects
United States · Title 33 — NAVIGATION AND NAVIGABLE WATERS · Status: effective
Cite this
- Citation
- 33 U.S.C. § 598c, Easements for hurricane and storm damage reduction projects, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/468525
- Permanent ID
ys:prov:468525@1- SHA-256
cf0631ec1e27e4eb21e5d0e9d7fab9fd8996ba56627efaf82880c88bcd2d5b14
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
With respect to a project for hurricane and storm damage reduction for which the Secretary is requiring a perpetual easement, the Secretary shall, upon request by the non-Federal interest for the project, certify real estate availability and proceed to construction of such project with a nonperpetual easement if—
the Secretary provides the non-Federal interest with formal notice that, in the event in which the nonperpetual easement expires and is not extended, the Secretary will be unable to—
For any project for hurricane storm damage risk reduction, or a proposal to modify such a project, that is authorized after January 4, 2025, for which a perpetual easement is required for Federal participation in the project, the Secretary shall include in the report of the Chief of Engineers for the project a disclosure of such requirement.
To the maximum extent practicable, the Secretary shall, at the request of the non-Federal interest for a project for hurricane storm damage risk reduction, identify and accept the minimum real estate interests necessary to carry out the project, in accordance with section 598b of this title.
During the 2-year period beginning on January 4, 2025, notwithstanding any requirement of the Secretary for a covered project to comply with the memorandum of the Corps of Engineers entitled “Standard Estates – Perpetual Beach Nourishment and Perpetual Restrictive Dune Easement” and dated August 4, 1995, the Secretary shall carry out each covered project in a manner consistent with the previously completed initial construction and periodic nourishments of the project, including repair and restoration work on the project under section 701n(a) of this title.
In this subsection, the term “covered project” means an authorized project for hurricane and storm damage reduction in any one of the following locations:
It is the sense of Congress that, for the purpose of constructing and maintaining a project for hurricane and storm damage risk reduction, the minimum estate necessary for easements may not exceed the life of the project nor be less than 50 years.
Nothing in this section may be construed to affect the requirements of section 2213(d) of this title.
Legislative history
The public laws that enacted or amended this section. Tallies are for the whole bill as it passed each chamber — often an omnibus covering far more than this provision — not a vote on this section alone.
- Thomas R. Carper Water Resources Development Act of 2024House: 399–18Senate: no recorded tally