33 U.S.C. § 2347a
Determination of project completion
United States · Title 33 — NAVIGATION AND NAVIGABLE WATERS · Status: effective
Cite this
- Citation
- 33 U.S.C. § 2347a, Determination of project completion, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/469466
- Permanent ID
ys:prov:469466@1- SHA-256
a0a2c2fe212f837c81013eb7022a640086b91f4ca01001ad9c6f937b9f04d1a1
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
The Secretary shall notify the applicable non-Federal interest when construction of a water resources project or a functional portion of the project is completed so the non-Federal interest may commence responsibilities, as applicable, for operating and maintaining the project.
Not later than 7 days after receiving a notification under subsection (a), the non-Federal interest may appeal the completion determination of the Secretary in writing with a detailed explanation of the basis for questioning the completeness of the project or functional portion of the project.
On notification that a non-Federal interest has submitted an appeal under paragraph (1), the Secretary shall contract with 1 or more independent, non-Federal experts to evaluate whether the applicable water resources project or functional portion of the project is complete.
An independent review carried out under subparagraph (A) shall be completed not later than 180 days after the date on which the Secretary receives an appeal from a non-Federal interest under paragraph (1).