33 U.S.C. § 2347b
Purpose and need
United States · Title 33 — NAVIGATION AND NAVIGABLE WATERS · Status: effective
Cite this
- Citation
- 33 U.S.C. § 2347b, Purpose and need, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/469467
- Permanent ID
ys:prov:469467@1- SHA-256
aef301d9e968bf358324c3de7b11f0b4ff3f74ad7a880fb8a5d0a47e449e0091
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Not later than 90 days after the date of receipt of a complete application for a water storage project, the District Engineer shall develop and provide to the applicant a purpose and need statement that describes—
No environmental impact statement or environmental assessment required under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) shall substantially commence with respect to a water storage project until the date on which the District Engineer provides to the applicant a purpose and need statement as required under paragraph (1).
A non-Federal interest may use the administrative appeals process described in part 331 of title 33, Code of Federal Regulations (or any succeeding regulation), in relation to a decision of the Secretary related to an application for a water storage project.