§ 176.80 Exceptions.

United States · 2 CFR — Federal Financial Assistance · Status: effective

Get this as JSONEmbed this
Cite this
Citation
2 CFR 176.80, § 176.80 Exceptions, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/497
Permanent ID
ys:prov:497@1
SHA-256
1540044ac1481c55f4ebabfb335aee082b75c740099e1af1a892995ce2b66207

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) When one of the following exceptions applies in a case or category of cases, the award official may allow the recipient to use foreign iron, steel and/or manufactured goods in the project without regard to the restrictions of section 1605 of the Recovery Act: (1) Nonavailability. The head of the Federal department or agency may determine that the iron, steel or relevant manufactured good is not produced or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality. The determinations of nonavailability of the articles listed at 48 CFR 25.104(a) and the procedures at 48 CFR 25.103(b)(1) also apply if any of those articles are manufactured goods needed in the project. (2) Unreasonable cost. The head of the Federal department or agency may determine that the cost of domestic iron, steel, or relevant manufactured goods will increase the cost of the overall project by more than 25 percent in accordance with § 176.110. (3) Inconsistent with public interest. The head of the Federal department or agency may determine that application of the restrictions of section 1605 of the Recovery Act would be inconsistent with the public interest. (b) When a determination is made for any of the reasons stated in this section that certain foreign iron, steel, and/or manufactured goods may be used— (1) The award official shall list the excepted materials in the award; and (2) The head of the Federal department or agency shall publish a notice in the Federal Register within two weeks after the determination is made, unless the item has already been determined to be domestically nonavailable. A list of items that are not domestically available is at 48 CFR 25.104(a). The Federal Register notice or information from the notice may be posted by OMB to Recovery.gov. The notice shall include— (i) The title “Buy American Exception under the American Recovery and Reinvestment Act of 2009”; (ii) The dollar value and brief description of the project; and (iii) A detailed written justification as to why the restriction is being waived.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.