13 CFR 305.11
§ 305.11 Contract awards; early construction start.
United States · 13 CFR — Business Credit and Assistance · Status: effective
Cite this
- Citation
- 13 CFR 305.11, § 305.11 Contract awards; early construction start, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/53203
- Permanent ID
ys:prov:53203@1- SHA-256
66111a2dce2b70c489030a6d6d2b02b3975f18caa2d27a17605e1073244aba98
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
EDA must determine that the award of all contracts necessary for design and construction of the Project facilities is in compliance with the terms and conditions of the Investment award in order for the costs to be eligible for EDA reimbursement. Pending this determination, the Recipient may issue a notice permitting construction under the contract to commence. If construction commences prior to EDA's determination, the Recipient proceeds at its own risk until EDA review and concurrence. The EDA regional office will advise the Recipient of the requirements necessary to obtain EDA's determination.