yourstate.us
14 CFR 35.35

§ 35.35 Centrifugal load tests.

United States · 14 CFR — Aeronautics and Space · Status: effective

Get this as JSONEmbed this
Cite this
Citation
14 CFR 35.35, § 35.35 Centrifugal load tests, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/55174
Permanent ID
ys:prov:55174@1
SHA-256
4bcf7fc7880cc42486a4839925185596a9e20baae3378de1c4e7e0a9e290b077

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

The applicant must demonstrate that a propeller complies with paragraphs (a), (b) and (c) of this section without evidence of failure, malfunction, or permanent deformation that would result in a major or hazardous propeller effect. When the propeller could be sensitive to environmental degradation in service, this must be considered. This section does not apply to fixed-pitch wood or fixed-pitch metal propellers of conventional design. (a) The hub, blade retention system, and counterweights must be tested for a period of one hour to a load equivalent to twice the maximum centrifugal load to which the propeller would be subjected during operation at the maximum rated rotational speed. (b) Blade features associated with transitions to the retention system (for example, a composite blade bonded to a metallic retention) must be tested either during the test of paragraph (a) of this section or in a separate component test for a period of one hour to a load equivalent to twice the maximum centrifugal load to which the propeller would be subjected during operation at the maximum rated rotational speed. (c) Components used with or attached to the propeller (for example, spinners, de-icing equipment, and blade erosion shields) must be subjected to a load equivalent to 159 percent of the maximum centrifugal load to which the component would be subjected during operation at the maximum rated rotational speed. This must be performed by either: (1) Testing at the required load for a period of 30 minutes; or (2) Analysis based on test.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.