14 CFR 77.3
§ 77.3 Definitions.
United States · 14 CFR — Aeronautics and Space · Status: effective
Cite this
- Citation
- 14 CFR 77.3, § 77.3 Definitions, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/55788
- Permanent ID
ys:prov:55788@1- SHA-256
57611544aba4aec22311f82222ed706a1f40894e01dc07f2d16b0ec17cab02ab
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
For the purpose of this part:
Non-precision instrument runway means a runway having an existing instrument approach procedure utilizing air navigation facilities with only horizontal guidance, or area type navigation equipment, for which a straight-in non-precision instrument approach procedure has been approved, or planned, and for which no precision approach facilities are planned, or indicated on an FAA planning document or military service military airport planning document.
Planned or proposed airport is an airport that is the subject of at least one of the following documents received by the FAA:
(1) Airport proposals submitted under 14 CFR part 157.
(2) Airport Improvement Program requests for aid.
(3) Notices of existing airports where prior notice of the airport construction or alteration was not provided as required by 14 CFR part 157.
(4) Airport layout plans.
(5) DOD proposals for airports used only by the U.S. Armed Forces.
(6) DOD proposals on joint-use (civil-military) airports.
(7) Completed airport site selection feasibility study.
Precision instrument runway means a runway having an existing instrument approach procedure utilizing an Instrument Landing System (ILS), or a Precision Approach Radar (PAR). It also means a runway for which a precision approach system is planned and is so indicated by an FAA-approved airport layout plan; a military service approved military airport layout plan; any other FAA planning document, or military service military airport planning document.
Public use airport is an airport available for use by the general public without a requirement for prior approval of the airport owner or operator.
Seaplane base is considered to be an airport only if its sea lanes are outlined by visual markers.
Utility runway means a runway that is constructed for and intended to be used by propeller driven aircraft of 12,500 pounds maximum gross weight and less.
Visual runway means a runway intended solely for the operation of aircraft using visual approach procedures, with no straight-in instrument approach procedure and no instrument designation indicated on an FAA-approved airport layout plan, a military service approved military airport layout plan, or by any planning document submitted to the FAA by competent authority.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.