Tex. Water Code § 49.2127
PIPELINE FEES AND REQUIREMENTS IMPOSED BY CERTAIN DISTRICTS
Texas · Texas Water Code · Status: effective
Cite this
- Citation
- Tex. Water Code § 49.2127, PIPELINE FEES AND REQUIREMENTS IMPOSED BY CERTAIN DISTRICTS, Texas, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/580674
- Permanent ID
ys:prov:580674@1- SHA-256
43a16788db2dd0433ae111e269f2e5af1f88ea3817b15525d82a95bb0c574bf9
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) In this section:
(1) "Developer" means a person who owns land in a district who:
(A) has divided or proposes to divide the land into two or more parts; or
(B) requests more than two water or sewer service connections on a single contiguous tract of land.
(2) "Retail public utility" has the meaning assigned by Section 13.002.
(b) This section applies only to a district whose territory is located wholly or partly in a county:
(1) located on the Gulf of Mexico and an international border; or
(2) adjacent to a county described by Subdivision (1).
(c) Notwithstanding Section 49.002, this section prevails over a special law governing a district.
(d) A district may not impose on a retail public utility that proposes to construct a water or sewer pipeline or associated infrastructure in the district's service area:
(1) requirements for constructing the pipeline that are unduly burdensome; or
(2) a fee that is greater than the actual, reasonable, and documented costs incurred by the district for review, legal services, engineering services, inspection, construction, and repair associated with the retail public utility construction, and any other related costs incurred by the district in association with the retail public utility construction.
(e) A district may not impose on a developer that proposes to construct a water or sewer pipeline or associated infrastructure in the district's service area a fee that is greater than the actual, reasonable, and documented costs incurred by the district for review, legal services, engineering services, inspection, construction, repair, and infrastructure relocation or conversion associated with the construction, and any other related costs incurred by the district in association with the construction of a subdivision.