14 CFR — Aeronautics and Space
Appendix A to Part 1204—Items To Cover in Memoranda of Agreement
United States · 14 CFR — Aeronautics and Space · Status: effective
Cite this
- Citation
- 14 CFR — Aeronautics and Space, Appendix A to Part 1204—Items To Cover in Memoranda of Agreement, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/60041
- Permanent ID
ys:prov:60041@1- SHA-256
f6f0ef4e2b003e48e5fbb4b37301c681ce0837d1c57741253ad47b18468abb43
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
The items to be covered in Memoranda of Agreement between NASA Installations and state and areawide OMB Circular A-95 clearinghouses for coordinating NASA and civilian planning:
1. Clearinghouses will be contacted at the earliest practicable point in project planning. Generally, this will be during the preparation of Preliminary Engineering Reports, or possibly earlier if meaningful information is available that could practically serve as an input in the decision-making process. It should be noted that clearinghouses are generally comprehensive planning agencies. As such, they are often the best repositories of information required for development planning and constitute a resource that can often save Federal planners substantial time and effort, if consulted early enough. In addition to providing information necessary for preliminary engineering, clearinghouses can make useful inputs to the development of environmental impact statements, as well as in reviewing draft statements. Thus, consultation at the earliest stage in planning can have substantial payoffs in installation development.
2. Clearinghouses will be afforded a minimum time of 30 days in which to review and comment on a proposed project and a maximum time of 45 days in which to complete such review.
3. The minimum information to be provided to the clearinghouse will consist of project description, scope and purpose, summary technical data, maps and diagrams where relevant, and any data which would show the relationship of the proposed project or action to applicable land use plans, policies, and controls for the affected area.
4. Establish procedures for notifying clearinghouses of the actions taken on projects, such as implementation, timing, postponement, abandonment, and explaining, where appropriate, actions taken contrary to clearinghouse recommendations.