Tex. Government Code § 2251.0521
UNSIGNED CHANGE ORDER
Texas · Texas Government Code · Status: effective
Cite this
- Citation
- Tex. Government Code § 2251.0521, UNSIGNED CHANGE ORDER, Texas, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/663181
- Permanent ID
ys:prov:663181@1- SHA-256
1ed9b466c489986a2be466136736b84d937c5f245d7a5880e3186b8157768eff
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) In this section:
(1) "Public work contract" has the meaning assigned by Section 2253.001.
(2) "Subcontract" means a contract between a subcontractor and a vendor who is providing services under a public work contract.
(b) A vendor may elect not to proceed with additional work directed by a governmental entity under a public work contract if:
(1) the vendor has not received a written, fully executed change order for the governmental entity-directed additional work; and
(2) the aggregate actual or anticipated value of the additional work under the vendor's contract terms plus any previous governmental entity-directed additional work for which the vendor has not received a written, fully executed change order exceeds 10 percent of the vendor's original public work contract amount.
(c) A subcontractor may elect not to proceed with additional work directed by a vendor under a subcontract if:
(1) the subcontractor has not received a written, fully executed change order for the governmental entity-directed additional work from the vendor; and
(2) the aggregate actual or anticipated value of the additional work under the subcontractor's subcontract terms plus any previous governmental entity-directed additional work for which the subcontractor has not received a written, fully executed change order exceeds 10 percent of the subcontractor's subcontract amount.
(d) A vendor or subcontractor who elects not to proceed with additional work as provided by this section is not responsible for damages associated with the election not to proceed.