yourstate.us
Tex. Health and Safety Code § 752.003

TEMPORARY CLEARANCE OF LINES

Texas · Texas Health and Safety Code · Status: effective

Get this as JSONEmbed this
Cite this
Citation
Tex. Health and Safety Code § 752.003, TEMPORARY CLEARANCE OF LINES, Texas, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/675467
Permanent ID
ys:prov:675467@1
SHA-256
1655ea3f06ca892fb393d7502c033daa730e3d779515b7ff7801e6989790eda0

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) A person, firm, corporation, or association responsible for temporary work or a temporary activity or function closer to a high voltage overhead line than the distances prescribed by this chapter must notify the operator of the line at least 48 hours before the work begins. (b) A person, firm, corporation, or association may not begin the work, activity, or function under this section until the person, firm, corporation, or association responsible for the work, activity, or function and the owner or operator, or both, of the high voltage overhead line have negotiated a satisfactory mutual arrangement to provide temporary de-energization and grounding, temporary relocation or raising of the line, or temporary mechanical barriers to separate and prevent contact between the line and the material or equipment or the person performing the work, activity, or function. (c) The person, firm, corporation, or association responsible for the work, activity, or function shall pay the operator of the high voltage overhead line the actual expense incurred by the operator in providing the clearance prescribed in the agreement. The operator may require payment in advance and is not required to provide the clearance until the person, firm, corporation, or association responsible for the work, activity, or function makes the payment. (d) If the actual expense of providing the clearance is less than the amount paid, the operator of the high voltage overhead line shall refund the surplus amount.